With several code updates happening in '24-'25, staying compliant is crucial to avoid equipment failure or shutdown. Paulin Research Group is here to help you stay ahead with the latest updates for pressure vessels, piping and tanks. Check out the table and resources below for engineer-focused guidance.
Code Calendar of Events | ||
---|---|---|
Code | Anticipated Publication Date | Notes |
ASME B31.1 | October 2024 | Officially released on October 15, 2024. Update: These changes are implemented and available in PRG Release 2025.4.0.2787. |
PD 5500 | October 2024 |
Currently published. |
ASME B31.3 | December 27, 2024 |
Officially published on December 27, 2024. Update: These changes are implemented and available in the PRG Release 2025.4.0.2787. |
AWS D1.1 | March 2025 | Officially published on April 17, 2025. Update: Review of the 2025 AWS code books is currently in progress. |
ASME BPV VIII | May 2025 | The final round of proofs that are published to committee members for review. Update: ASME Section VIII, Div. 1 and Div. 2 proofs are now available and published to committee members for review. |
ASME BPV II, VIII & IX | July 2025 | Final publication date for ASME BPV VIII. |
PD 5500 | September–October 2025 |
|
EN 13445 | Unknown |
Historically this standard has an erratic publication cadence. We are keeping a close eye out on it. |
Code Calendar of Events | |
---|---|
Code | Anticipated Publication Date |
Notes | |
ASME B31.1 | October 2024 |
Officially released on October 15, 2024. Update: These changes are implemented and available in PRG Release 2025.4.0.2787. |
|
PD 5500 | October 2024 |
Currently published. | |
ASME B31.3 | December 27, 2024 |
Officially published on December 27, 2024. Update: These changes are implemented and available in the PRG Release 2025.4.0.2787. |
|
AWS D1.1 | March 2025 |
Officially published on April 17, 2025. Update: Review of the 2025 AWS code books is currently in progress. |
|
ASME BPV VIII | May 2025 |
The final round of proofs that are published to committee members for review. Update: ASME Section VIII, Div. 1 and Div. 2 proofs are now available and published to committee members for review. |
|
ASME BPV II, VIII & IX | July 2025 |
Final publication date for ASME BPV VIII. | |
PD 5500 | September–October 2025 |
EN 13445 | Unknown |
Historically this standard has an erratic publication cadence. We are keeping a close eye out on it. |